Data Center Fuel Supply Agreements: What to Put in the SLA

Your tanks buy you hours. The agreement decides what happens after that. Write down response, priority, trucks, backup sources and keep-full terms while the grid is still on.

12 hUptime fuel floor at N
24 h+Typical design target
7,500Gal per transport load
3.8Loads a day, 15 MW plant
Outage plan agreed in advance
Scheduled fills after tests
24/7/365 dispatch
800-720-4546
Quick Answer

A data center fuel supply agreement should spell out how an outage order is placed and answered, the arrival window each site can expect, what "priority" means when every generator in the region is running, committed trucks and loads, backup supply sources, keep-full triggers, fuel quality, site access and records. Agree it before the outage.

Why it matters

Why a data center needs a fuel supply agreement, not just a fuel vendor

On-site fuel is a bridge, not a plan. Uptime Institute's Tier Standard sets a floor of 12 hours of on-site fuel at N load for every Tier, and Consulting-Specifying Engineer notes that critical facilities such as data centers are typically expected to support the load for 24 hours or more. Where NFPA 110 applies, its Class is the hours the system is designed to run at rated load without refueling. Every one of those numbers ends with a truck. How many gallons that takes is in our data center diesel sizing guide; this page is about the agreement that gets the truck there.

Normal deliveries prove nothing about a regional outage. A supplier that tops you off on time every month is serving one customer on a quiet day. In a storm, every hospital, tower site, water plant and data center in the region calls at once, and the same trucks, drivers and terminal racks have to cover all of them. Consulting-Specifying Engineer warns that it's common for a fuel vendor to promise one type of truck and then, in a city-wide outage when everyone needs fuel, for that truck not to be available.

It has happened. After Hurricane Sandy in 2012, Data Center Knowledge reported that data center providers typically arrange priority contracts with fuel suppliers, and asked the obvious question: what happens when a regional disaster creates dueling priorities? New Jersey providers found fuel, though some had to go outside the region to keep it coming, and flooding made some Manhattan roads impassable. In 2005, a New Orleans colocation provider had to scramble for diesel while the city was without power after Katrina.

"We had 10 days of fuel, and contracts with two fuel suppliers. You also have to make sure your fuel suppliers can operate with no power, and have gravity-fed systems."

Paul Hines, Sentinel Data Centers (central New Jersey), on Sandy, quoted by Data Center Knowledge, March 2013

FEMA's guide to emergency power for critical facilities (FEMA P-1019) makes the same point in checklist form: its pre-disaster list includes preferred customer agreements with fuel suppliers to assure delivery, and its planning section calls for contracts with fuel suppliers including delivery, alternative fuel sources, and the ability and authorization to deliver fuel and filters into restricted disaster zones. For general contract structure, see fuel supply agreements; the rest of this page is specific to generator plants.

The clauses

What to put in a data center fuel SLA

Twelve terms cover most of it. If a line below isn't in your current agreement, that's the gap to close first.

TermWhat to put in writingQuestion to ask
Sites and tanksEvery site, each tank's capacity and usable gallons, fill-point fittings and heights, generator count and burn at design load, and the fuel grade."Is every one of our sites on file today, and when was it last checked?"
OrderingHow an outage order is placed (phone, portal or a monitoring alarm), 24/7 contacts on both sides, and how quickly a person acknowledges the order."Who answers at 3 a.m.: a dispatcher or a callback service?"
Arrival windowThe window each site can expect in normal conditions and in a regional emergency, written as a separate number from the answer time."From which terminal would our fuel come, and how long is the drive?"
PriorityWhere your sites rank against non-contract callers and against the supplier's other critical customers, and what decides the order between them."How many other critical sites depend on the trucks that would serve us?"
CapacityTrucks, drivers and transport loads per day committed to your sites during an extended outage, and for how many days."How many loads a day can you sustain for us on day three?"
Supply sourcesPrimary and alternate terminals, out-of-region sourcing, and whether the supplier's own yard and pumps run without grid power."If your usual terminal is down or rationing, where does our fuel come from?"
Keep-fullA refill trigger level for each tank, top-offs after every test run and load-bank test, and a pre-storm top-off when a forecast turns bad."What triggers a delivery without anyone on our side calling?"
Fuel spec and qualityThe grade (for example ASTM D975 No. 2-D S15, dyed for stationary generators, or renewable diesel where the engine maker approves it), testing, polishing, and the remedy if delivered fuel fails a test."Who pays if fuel you delivered comes back off-spec?"
AccessSecurity, badging and escort steps, delivery windows, the truck type and pump capability your fill points need, and how the supplier gets into a restricted area."What truck will you actually send in a city-wide outage?"
RecordsA ticket for every fill: tank, product, gallons, date and time, in a format your customers' reports and your auditors can use."Can you report deliveries by tank, not just by site?"
PriceHow emergency deliveries are priced: the contract price, an index, or a stated premium, with after-hours and surge fees listed."Does our contract price still apply in a declared emergency?"
Force majeureWhich events excuse the supplier, what it still owes when they happen (notice, alternate sourcing), and your remedies if it doesn't deliver."If you're excused, how fast do you tell us, and what do you still do?"

Add a thirteenth line if you can: an annual review of sites, contacts and volumes, plus a test order or tabletop drill.

Response time: answer, window and arrival are three different numbers

"Response time" in a fuel SLA often means how fast someone picks up, not how fast fuel arrives. Write them separately. The answer time is in the supplier's control. The arrival window depends on distance to the terminal, traffic, weather and site access, so it has to be set per site, not company-wide. Then work backward: your refill trigger has to hold enough fuel to cover the arrival window plus a margin. A plant burning 1,185 gallons an hour, the 15 MW example in our resupply math, uses 14,220 gallons in a 12-hour window. Run your own sets through the generator fuel calculator or the consumption chart.

Priority

Emergency delivery priority: what it can and can't promise

"Priority" is the word most often in a fuel agreement and least often defined. Ask the supplier to put three things in writing:

  1. Who you're ahead of. Priority over callers with no account is common and cheap to give. Priority among the supplier's other contracted critical sites is the one that matters in a regional outage, and the hardest to promise.
  2. What it's measured against. Trucks and drivers are finite. If a supplier has promised "first in line" to more sites than it can fill in a day, the promise is oversubscribed. Ask how many critical accounts sit on the same fleet in your region.
  3. What happens upstream. Your supplier's priority to you is only as good as its own access to fuel. During the 2019 Hurricane Dorian scare, the head of the Florida Petroleum Marketers Association told FreightWaves the problem was "too many trucks, not enough racks," and suppliers tend to raise unbranded rack prices sharply in a shortage so branded customers get served first.

Uptime Institute's own list of questions for owners includes two that belong in this conversation word for word: "What fuel service can be provided in a local disaster, and can local suppliers meet fuel requirements?" and "What fuel service can be provided in a regional emergency, and within what time period?"

Backup sources

Multiple fuel sources: how many is enough?

One contract is a single point of failure, the same as one generator with no spare. Think of fuel supply in layers:

Layer 1

Fuel already on site

The only source nobody else can claim. Keep it full and keep it clean. A tank of degraded fuel is runtime on paper only; see how long diesel lasts.

Layer 2

Primary supplier under contract

The agreement on this page: sites on file, keep-full program, outage plan, defined priority and committed loads.

Layer 3

A second supplier, set up in advance

An account with sites already on file, so a call becomes a dispatch. Two suppliers loading at the same terminal are closer to one source than two, so ask where each one loads.

Layer 4

Out-of-region and extra storage

Sourcing from outside the storm's footprint, as some New Jersey providers did after Sandy, and rented tanks that stretch runtime when the gap is too long.

An out-of-region source solves supply, not access. The Sentinel executive who added one after Sandy said it still "doesn't solve the problem of access to facilities." Agree access before the event: who meets the truck, what it needs to clear security, and whether fill points can be reached with the hose and pump the supplier will bring. Fill points high above the truck change the equipment needed; Consulting-Specifying Engineer notes that a gravity truck alone won't work when the tank sits higher than the truck. For high-rise tanks, see rooftop generator fueling.

Keep-full

Keep-full terms: the clause that prevents most emergencies

The cheapest emergency delivery is the one you never need, because the tanks were full when the utility failed. A keep-full clause should name:

  • A trigger level per tank, set from the arrival window above, not a round number.
  • Who watches the level. With tank monitoring, the supplier sees it too and can schedule the refill; without it, name the person who checks and how often.
  • Top-offs after every test run and load-bank test, so the tank is back to its required level before the next real start.
  • A pre-storm top-off when a hurricane or winter storm is forecast, before every other site in the region asks for the same thing.
  • Fuel quality alongside volume. A full tank of fuel that sits for years needs testing and, when results call for it, polishing. Our data center fuel guide covers the schedule; polishing vs. tank cleaning covers the difference.
Price and fine print

Pricing, force majeure and the fine print

Price. Decide how emergency gallons are priced before you need them: under the contract price, at an index, or at a stated premium. A fixed price covers the base volume; check whether it extends to emergency loads. See fixed-price diesel contracts, how bulk diesel is priced and the weekly diesel price report.

Force majeure. Most supply contracts have a clause that excuses performance when an extraordinary event outside a party's control prevents it, such as a fire, flood or storm. Cornell's Legal Information Institute notes that courts generally read these clauses narrowly, and that some jurisdictions, such as New York, only excuse events the clause actually names. For a data center, the risk is obvious: the disaster that knocks out the grid can be the same event that excuses the fuel supplier. Read what the clause covers, and what the supplier still has to do when it applies.

Records. Every fill should come with a ticket by tank, product and gallons, so you can reconcile deliveries against generator runtime and report to your own customers. See how to read a fuel delivery ticket.

⚠ Not legal advice

This page is general information about what buyers commonly ask for in fuel supply agreements. It isn't legal advice, and contract law varies by state. Have your counsel review any fuel supply agreement, especially the force majeure, liability and remedies clauses, before you sign it.

Red flags

Red flags in a generator fuel SLA

  • "Priority" with no definition of who you're ahead of.
  • A "response time" that is really a callback time, with no arrival window.
  • No truck or load commitment for an outage that lasts more than a day.
  • One terminal, no alternate, and no answer on how the supplier runs without power.
  • Force majeure that excuses "supply shortages" with no notice duty and no fallback.
  • Nothing on top-offs after tests, so tanks drift down between real outages.
  • Nothing on fuel quality, or no say in who pays when delivered fuel fails a test.
  • Sites not on file until the first emergency call.
FuelGo

How FuelGo supports a data center fuel program

FuelGo runs generator plant fuel as one program on one account, set up while the grid is still on: scheduled fills after weekly or monthly tests, fuel monitoring that tracks levels across every generator and schedules deliveries, and an outage response plan that fixes the delivery sequence, truck count and site access in advance. During regional outages, critical facilities like data centers are prioritized in emergency dispatch, and customers with site details already on file are dispatched first. Dispatch is staffed 24/7/365, and a person answers.

We don't quote a blanket response time. Arrival depends on your location, the distance to the nearest terminal, site access and what's happening across the region, so the dispatcher gives you a realistic window for your site. If you already have a primary supplier, getting your sites on file with us before storm season means the day your usual supplier can't deliver is a phone call, not an onboarding.

We deliver dyed diesel for stationary generators, clear diesel and R99 renewable diesel nationwide, 20 to 4,400 gallons per drop and transport loads up to 7,500 gallons. R99 isn't at every terminal; where it can't be pulled locally it ships by rail or barge, so confirm lead time before you commit a site to it. Stored fuel gets lab fuel testing and polishing for tanks from 50 to 50,000 gallons, plus tank cleaning and pump-out, and rental tanks from 119 to 17,000 gallons extend runtime. Ask about storm pre-positioning when a forecast turns. Pricing can be fixed, priced off NYMEX NY Harbor ULSD futures, or indexed. Fills are itemized by gallons, date and tank, with invoicing through ARIBA or COUPA, and we take credit card, ACH or check.

See data center fuel delivery, generator fuel delivery and emergency fuel delivery, get a delivered quote or call 800-720-4546. A dispatcher replies within the hour.

Common questions

Data center fuel supply agreement FAQ

What is a data center fuel supply agreement?
A contract with a fuel supplier that covers how the generator plant's diesel is kept full, tested and resupplied, including during a utility outage. Beyond price and volume, it should set how outage orders are placed, the arrival window for each site, priority during regional emergencies, committed trucks and loads, backup sources, keep-full triggers, fuel quality, site access and records.
What response time should a generator fuel SLA include?
Write two numbers, not one: how fast a person acknowledges an outage order, and the arrival window for each site in normal conditions and in a regional emergency. Arrival depends on distance to the terminal and site access, so a single company-wide figure means little. Set each tank's refill trigger to hold enough fuel to cover that arrival window plus a margin.
Can a fuel supplier guarantee priority during a regional emergency?
It can rank you, but only within the trucks, drivers and fuel it can get. Ask who you're ahead of (callers with no account, or its other critical customers too), how many critical sites share the same fleet in your region, and where its fuel comes from if its usual terminal is down. After Sandy, providers with priority contracts still faced competing priorities and impassable roads.
Should a data center have more than one fuel supplier?
For critical sites, yes. FEMA's emergency power guide lists contracts with fuel suppliers and alternative fuel sources in its planning checklist, and one New Jersey operator went through Sandy with 10 days of fuel and contracts with two suppliers, then added an out-of-region supplier. Check that the two suppliers don't load at the same terminal, and get your sites on file with both.
What is a keep-full fuel program for data center generators?
A standing arrangement in which the supplier refills each tank when it falls to an agreed trigger level, tops it off after test runs and load-bank tests, and fills it ahead of a forecast storm. With tank monitoring, refills follow the actual level instead of someone remembering to call. It's the clause that keeps most outages from becoming fuel emergencies.
Does force majeure excuse a fuel supplier during a disaster?
It can. Force majeure clauses excuse performance when an extraordinary event outside a party's control, such as a storm or flood, prevents it, and courts generally read them narrowly. Because the disaster that cuts power can be the same event that excuses delivery, read what the clause covers and what the supplier still owes. This isn't legal advice; have counsel review it.
How much fuel should be on site before the agreement takes over?
Enough for the strictest of your design standard, code and customer commitments. Uptime Institute's Tier Standard sets at least 12 hours at N load, and data centers are typically expected to support the load for 24 hours or more. On-site fuel has to last at least as long as the supplier's arrival window, with margin, and longer in a regional emergency.
Who is responsible for fuel quality under a supply agreement?
Split it in writing. The supplier should deliver fuel that meets the agreed grade, such as ASTM D975 No. 2-D S15, and stand behind it if a test shows otherwise. Once it's in your tanks, keeping it clean through testing and polishing is usually the owner's job or a contracted service. Spell out who pays for remediation in each case.

Sources: Uptime Institute Journal, Fuel System Design and Reliability (12 hours at N for all Tiers; supplier questions for local disaster and regional emergency) · Consulting-Specifying Engineer, The nine major steps of designing generator fuel systems, June 2016 (24 hours or more; vendor truck in a city-wide outage; gravity truck and tank height) · Consulting-Specifying Engineer, NFPA 110-2019 concepts and changes (Class definition) · Data Center Knowledge, How Sandy Has Altered Data Center Disaster Planning, March 13, 2013 (priority contracts; dueling priorities; out-of-region supply; Sentinel quotes; Manhattan roads) · Data Center Knowledge, Securing Diesel Delivery in Disasters, Sept. 2, 2008 (New Orleans colocation provider after Katrina) · FEMA P-1019, Emergency Power Systems for Critical Facilities, Sept. 2014 (section 3.2.2 and Table D-1) · FreightWaves, Mixed information coming out of Florida on diesel fuel availability, Aug. 30, 2019 · Cornell Legal Information Institute, Force majeure · ASTM D975-25, Standard Specification for Diesel Fuel. The 1,185 gal/hr, 3.8 loads a day and 15 MW figures are from our data center sizing guide.